# Issues 920 (#34#45): Dependency Analysis & Two-Person Split
Scope: the twelve "Structure migrations" sub-issues of #26 (Eliminating
EventBridge), GitHub issues #34#45. Each is independently shippable; this
document captures the real ordering constraints so two people can work in
parallel without stepping on each other.
## Hard dependencies
Only two kinds exist:
1. **The issue 7 signal (`Core::undo_index_changed`)** — required by issues
9, 11, 15, 16 (and used by 10/12/13/17 for undo refresh).
✅ Already landed in `a030f2da2` (issue 7 / #55). **No longer blocks
anything.**
2. **The issue 15 "project load finished" hook** (`Core` broadcasts after
TaskDialog load success). Explicitly reused by:
- **issue 13 (#38)** — "re-read uniformly after undo/**load**"
- **issue 17 (#42)** — "undo and **load** rebuild uniformly"
- **issue 19 (#44)** — "on load completion do a uniform model reset
(**reuse the issue 15 hook**)"
Everything else has **no ordering constraints**.
## Dependency graph
```
issue 7 (done) ──┬─> 9, 10, 11, 12, 16 (undo refresh signal, available now)
└─> 15 ──┬─> 13 (project-load hook)
├─> 17
└─> 19
14, 18, 20 — fully independent
```
## File-overlap (merge-conflict) risks
| Pair | Overlap | Severity |
|------|---------|----------|
| 15 / 16 | both in `app/widget/nodeview/` (+ `mainwindow.cpp` in 16) | low — different files |
| 17 / 18 | both in `app/widget/timelinewidget/` (17 heavily edits `timelinewidget.cpp`) | medium — keep in the same person's queue |
| 12 / 13 / 14 | all under `app/widget/nodeparamview/` | low — different files |
| 9 / 10 | marker/workarea pattern is identical; not the same files | none, but cheap to do together |
## Suggested split
**Person A — "signals already available" batch (start immediately):**
- issue 9 (#34) — seekablewidget marker/workarea
- issue 10 (#35) — resizabletimelinescrollbar marker/workarea (same pattern as 9)
- issue 11 (#36) — nodeviewitem label/color/message/array
- issue 12 (#37) — NodeParamViewItem / arraywidget / keyframecontrol
- issue 14 (#39) — NodeParamView group passthrough / context
- issue 20 (#45) — misc leftovers
**Person B — "project-load hook" chain (15 first, then its dependents):**
- issue 15 (#40) — nodeviewcontext structure core + **add the load hook**
- issue 16 (#41) — nodeview NODE_REMOVED_FROM_GRAPH (same area as 15)
- issue 13 (#38) — nodeparamviewwidgetbridge values (needs the hook)
- issue 17 (#42) — timelinewidget track/block structure (needs the hook; keeps 18's neighbor in one queue)
- issue 18 (#43) — trackviewitem index/muted
- issue 19 (#44) — projectviewmodel folder/label (needs the hook)
Rationale: B owns everything that consumes the issue 15 hook, so the hook's
API is designed and used by one person with no cross-team blocking. A's
batch only needs the already-landed issue 7 signal, so both can start today.
Workload is ~6 × 0.5 day each side.
Ground rules still apply per issue: `cmake --build cmake-build-debug -j8 &&
cd cmake-build-debug && ctest -j4` must be green (122/122) before shipping,
and remove the matching `bridge_->subscribe` / `oakengine_event_subscribe`
calls when done.
@@ -0,0 +1,70 @@
# Issues 920#34–#45):依赖关系梳理与两人分工建议
范围:#26Eliminating EventBridge)的 12 个 "Structure migrations"
子任务,对应 GitHub issue #34#45。每个 issue 都可以独立交付,本文档
梳理真实的先后约束,让两个人可以并行推进而互不阻塞。
## 硬依赖
只有两类:
1. **issue 7 的信号(`Core::undo_index_changed`** —— issue 9、11、
15、16 明确依赖它(10/12/13/17 的 undo 刷新也要用)。
✅ 已在 `a030f2da2` 落地(issue 7 / #55)。**不再构成阻塞。**
2. **issue 15 新增的 "project load finished" 钩子**Core 在 TaskDialog
加载成功后广播)。明确复用它的有:
- **issue 13#38** —— "re-read uniformly after undo/**load**"
- **issue 17#42** —— "undo and **load** rebuild uniformly"
- **issue 19#44** —— "on load completion do a uniform model
reset**复用 issue 15 的钩子**"
其余 issue **没有任何先后约束**
## 依赖图
```
issue 7(已完成) ──┬─> 9, 10, 11, 12, 16 undo 刷新信号,现已可用)
└─> 15 ──┬─> 13 (项目加载钩子)
├─> 17
└─> 19
14、18、20 —— 完全独立
```
## 文件重叠(合并冲突)风险
| 组合 | 重叠区域 | 程度 |
|------|---------|------|
| 15 / 16 | 都在 `app/widget/nodeview/`16 还涉及 `mainwindow.cpp` | 低——不同文件 |
| 17 / 18 | 都在 `app/widget/timelinewidget/`17 会大改 `timelinewidget.cpp`) | 中——建议排在同一个人的队列里 |
| 12 / 13 / 14 | 都在 `app/widget/nodeparamview/` 下 | 低——不同文件 |
| 9 / 10 | marker/workarea 的处理模式完全相同,但不是同一批文件 | 无冲突,但连着做成本低 |
## 建议分工
**A 同学 —— "信号已就绪" 批次(今天就能开始):**
- issue 9#34)—— seekablewidget marker/workarea
- issue 10#35)—— resizabletimelinescrollbar marker/workarea(与 9 同模式)
- issue 11#36)—— nodeviewitem label/color/message/array
- issue 12#37)—— NodeParamViewItem / arraywidget / keyframecontrol
- issue 14#39)—— NodeParamView group passthrough / context
- issue 20#45)—— 零散收尾
**B 同学 —— "项目加载钩子" 链(先做 15,再做它的下游):**
- issue 15#40)—— nodeviewcontext 结构核心 + **新增加载钩子**
- issue 16#41)—— nodeview NODE_REMOVED_FROM_GRAPH(与 15 同区域)
- issue 13#38)—— nodeparamviewwidgetbridge 参数值(依赖钩子)
- issue 17#42)—— timelinewidget track/block 结构(依赖钩子;同时把 18 的邻域保持在同一队列)
- issue 18#43)—— trackviewitem index/muted
- issue 19#44)—— projectviewmodel folder/label(依赖钩子)
理由:所有消费 issue 15 钩子的 issue 都归 B,钩子的 API 由同一个人
设计并使用,零跨人阻塞;A 的批次只依赖已经落地的 issue 7 信号,
两人今天都能开工。工作量两侧均约为 6 × 0.5 天。
每个 issue 的通用要求不变:提交前
`cmake --build cmake-build-debug -j8 && cd cmake-build-debug && ctest -j4`
必须全绿(122/122),完成后移除对应的
`bridge_->subscribe` / `oakengine_event_subscribe` 调用。