docs: dependency analysis and two-person split for issues 9-20 (#34-#45)
This commit is contained in:
@@ -0,0 +1,73 @@
|
||||
# Issues 9–20 (#34–#45): Dependency Analysis & Two-Person Split
|
||||
|
||||
Scope: the twelve "Structure migrations" sub-issues of #26 (Eliminating
|
||||
EventBridge), GitHub issues #34–#45. Each is independently shippable; this
|
||||
document captures the real ordering constraints so two people can work in
|
||||
parallel without stepping on each other.
|
||||
|
||||
## Hard dependencies
|
||||
|
||||
Only two kinds exist:
|
||||
|
||||
1. **The issue 7 signal (`Core::undo_index_changed`)** — required by issues
|
||||
9, 11, 15, 16 (and used by 10/12/13/17 for undo refresh).
|
||||
✅ Already landed in `a030f2da2` (issue 7 / #55). **No longer blocks
|
||||
anything.**
|
||||
|
||||
2. **The issue 15 "project load finished" hook** (`Core` broadcasts after
|
||||
TaskDialog load success). Explicitly reused by:
|
||||
- **issue 13 (#38)** — "re-read uniformly after undo/**load**"
|
||||
- **issue 17 (#42)** — "undo and **load** rebuild uniformly"
|
||||
- **issue 19 (#44)** — "on load completion do a uniform model reset
|
||||
(**reuse the issue 15 hook**)"
|
||||
|
||||
Everything else has **no ordering constraints**.
|
||||
|
||||
## Dependency graph
|
||||
|
||||
```
|
||||
issue 7 (done) ──┬─> 9, 10, 11, 12, 16 (undo refresh signal, available now)
|
||||
└─> 15 ──┬─> 13 (project-load hook)
|
||||
├─> 17
|
||||
└─> 19
|
||||
14, 18, 20 — fully independent
|
||||
```
|
||||
|
||||
## File-overlap (merge-conflict) risks
|
||||
|
||||
| Pair | Overlap | Severity |
|
||||
|------|---------|----------|
|
||||
| 15 / 16 | both in `app/widget/nodeview/` (+ `mainwindow.cpp` in 16) | low — different files |
|
||||
| 17 / 18 | both in `app/widget/timelinewidget/` (17 heavily edits `timelinewidget.cpp`) | medium — keep in the same person's queue |
|
||||
| 12 / 13 / 14 | all under `app/widget/nodeparamview/` | low — different files |
|
||||
| 9 / 10 | marker/workarea pattern is identical; not the same files | none, but cheap to do together |
|
||||
|
||||
## Suggested split
|
||||
|
||||
**Person A — "signals already available" batch (start immediately):**
|
||||
|
||||
- issue 9 (#34) — seekablewidget marker/workarea
|
||||
- issue 10 (#35) — resizabletimelinescrollbar marker/workarea (same pattern as 9)
|
||||
- issue 11 (#36) — nodeviewitem label/color/message/array
|
||||
- issue 12 (#37) — NodeParamViewItem / arraywidget / keyframecontrol
|
||||
- issue 14 (#39) — NodeParamView group passthrough / context
|
||||
- issue 20 (#45) — misc leftovers
|
||||
|
||||
**Person B — "project-load hook" chain (15 first, then its dependents):**
|
||||
|
||||
- issue 15 (#40) — nodeviewcontext structure core + **add the load hook**
|
||||
- issue 16 (#41) — nodeview NODE_REMOVED_FROM_GRAPH (same area as 15)
|
||||
- issue 13 (#38) — nodeparamviewwidgetbridge values (needs the hook)
|
||||
- issue 17 (#42) — timelinewidget track/block structure (needs the hook; keeps 18's neighbor in one queue)
|
||||
- issue 18 (#43) — trackviewitem index/muted
|
||||
- issue 19 (#44) — projectviewmodel folder/label (needs the hook)
|
||||
|
||||
Rationale: B owns everything that consumes the issue 15 hook, so the hook's
|
||||
API is designed and used by one person with no cross-team blocking. A's
|
||||
batch only needs the already-landed issue 7 signal, so both can start today.
|
||||
Workload is ~6 × 0.5 day each side.
|
||||
|
||||
Ground rules still apply per issue: `cmake --build cmake-build-debug -j8 &&
|
||||
cd cmake-build-debug && ctest -j4` must be green (122/122) before shipping,
|
||||
and remove the matching `bridge_->subscribe` / `oakengine_event_subscribe`
|
||||
calls when done.
|
||||
@@ -0,0 +1,70 @@
|
||||
# Issues 9–20(#34–#45):依赖关系梳理与两人分工建议
|
||||
|
||||
范围:#26(Eliminating EventBridge)的 12 个 "Structure migrations"
|
||||
子任务,对应 GitHub issue #34–#45。每个 issue 都可以独立交付,本文档
|
||||
梳理真实的先后约束,让两个人可以并行推进而互不阻塞。
|
||||
|
||||
## 硬依赖
|
||||
|
||||
只有两类:
|
||||
|
||||
1. **issue 7 的信号(`Core::undo_index_changed`)** —— issue 9、11、
|
||||
15、16 明确依赖它(10/12/13/17 的 undo 刷新也要用)。
|
||||
✅ 已在 `a030f2da2` 落地(issue 7 / #55)。**不再构成阻塞。**
|
||||
|
||||
2. **issue 15 新增的 "project load finished" 钩子**(Core 在 TaskDialog
|
||||
加载成功后广播)。明确复用它的有:
|
||||
- **issue 13(#38)** —— "re-read uniformly after undo/**load**"
|
||||
- **issue 17(#42)** —— "undo and **load** rebuild uniformly"
|
||||
- **issue 19(#44)** —— "on load completion do a uniform model
|
||||
reset(**复用 issue 15 的钩子**)"
|
||||
|
||||
其余 issue **没有任何先后约束**。
|
||||
|
||||
## 依赖图
|
||||
|
||||
```
|
||||
issue 7(已完成) ──┬─> 9, 10, 11, 12, 16 (undo 刷新信号,现已可用)
|
||||
└─> 15 ──┬─> 13 (项目加载钩子)
|
||||
├─> 17
|
||||
└─> 19
|
||||
14、18、20 —— 完全独立
|
||||
```
|
||||
|
||||
## 文件重叠(合并冲突)风险
|
||||
|
||||
| 组合 | 重叠区域 | 程度 |
|
||||
|------|---------|------|
|
||||
| 15 / 16 | 都在 `app/widget/nodeview/`(16 还涉及 `mainwindow.cpp`) | 低——不同文件 |
|
||||
| 17 / 18 | 都在 `app/widget/timelinewidget/`(17 会大改 `timelinewidget.cpp`) | 中——建议排在同一个人的队列里 |
|
||||
| 12 / 13 / 14 | 都在 `app/widget/nodeparamview/` 下 | 低——不同文件 |
|
||||
| 9 / 10 | marker/workarea 的处理模式完全相同,但不是同一批文件 | 无冲突,但连着做成本低 |
|
||||
|
||||
## 建议分工
|
||||
|
||||
**A 同学 —— "信号已就绪" 批次(今天就能开始):**
|
||||
|
||||
- issue 9(#34)—— seekablewidget marker/workarea
|
||||
- issue 10(#35)—— resizabletimelinescrollbar marker/workarea(与 9 同模式)
|
||||
- issue 11(#36)—— nodeviewitem label/color/message/array
|
||||
- issue 12(#37)—— NodeParamViewItem / arraywidget / keyframecontrol
|
||||
- issue 14(#39)—— NodeParamView group passthrough / context
|
||||
- issue 20(#45)—— 零散收尾
|
||||
|
||||
**B 同学 —— "项目加载钩子" 链(先做 15,再做它的下游):**
|
||||
|
||||
- issue 15(#40)—— nodeviewcontext 结构核心 + **新增加载钩子**
|
||||
- issue 16(#41)—— nodeview NODE_REMOVED_FROM_GRAPH(与 15 同区域)
|
||||
- issue 13(#38)—— nodeparamviewwidgetbridge 参数值(依赖钩子)
|
||||
- issue 17(#42)—— timelinewidget track/block 结构(依赖钩子;同时把 18 的邻域保持在同一队列)
|
||||
- issue 18(#43)—— trackviewitem index/muted
|
||||
- issue 19(#44)—— projectviewmodel folder/label(依赖钩子)
|
||||
|
||||
理由:所有消费 issue 15 钩子的 issue 都归 B,钩子的 API 由同一个人
|
||||
设计并使用,零跨人阻塞;A 的批次只依赖已经落地的 issue 7 信号,
|
||||
两人今天都能开工。工作量两侧均约为 6 × 0.5 天。
|
||||
|
||||
每个 issue 的通用要求不变:提交前
|
||||
`cmake --build cmake-build-debug -j8 && cd cmake-build-debug && ctest -j4`
|
||||
必须全绿(122/122),完成后移除对应的
|
||||
`bridge_->subscribe` / `oakengine_event_subscribe` 调用。
|
||||