docs: dependency analysis and two-person split for issues 9-20 (#34-#45)

This commit is contained in:
2026-08-05 01:16:07 +08:00
parent 40eea8d97c
commit b55d626c0c
2 changed files with 143 additions and 0 deletions
+73
View File
@@ -0,0 +1,73 @@
# Issues 920 (#34#45): Dependency Analysis & Two-Person Split
Scope: the twelve "Structure migrations" sub-issues of #26 (Eliminating
EventBridge), GitHub issues #34#45. Each is independently shippable; this
document captures the real ordering constraints so two people can work in
parallel without stepping on each other.
## Hard dependencies
Only two kinds exist:
1. **The issue 7 signal (`Core::undo_index_changed`)** — required by issues
9, 11, 15, 16 (and used by 10/12/13/17 for undo refresh).
✅ Already landed in `a030f2da2` (issue 7 / #55). **No longer blocks
anything.**
2. **The issue 15 "project load finished" hook** (`Core` broadcasts after
TaskDialog load success). Explicitly reused by:
- **issue 13 (#38)** — "re-read uniformly after undo/**load**"
- **issue 17 (#42)** — "undo and **load** rebuild uniformly"
- **issue 19 (#44)** — "on load completion do a uniform model reset
(**reuse the issue 15 hook**)"
Everything else has **no ordering constraints**.
## Dependency graph
```
issue 7 (done) ──┬─> 9, 10, 11, 12, 16 (undo refresh signal, available now)
└─> 15 ──┬─> 13 (project-load hook)
├─> 17
└─> 19
14, 18, 20 — fully independent
```
## File-overlap (merge-conflict) risks
| Pair | Overlap | Severity |
|------|---------|----------|
| 15 / 16 | both in `app/widget/nodeview/` (+ `mainwindow.cpp` in 16) | low — different files |
| 17 / 18 | both in `app/widget/timelinewidget/` (17 heavily edits `timelinewidget.cpp`) | medium — keep in the same person's queue |
| 12 / 13 / 14 | all under `app/widget/nodeparamview/` | low — different files |
| 9 / 10 | marker/workarea pattern is identical; not the same files | none, but cheap to do together |
## Suggested split
**Person A — "signals already available" batch (start immediately):**
- issue 9 (#34) — seekablewidget marker/workarea
- issue 10 (#35) — resizabletimelinescrollbar marker/workarea (same pattern as 9)
- issue 11 (#36) — nodeviewitem label/color/message/array
- issue 12 (#37) — NodeParamViewItem / arraywidget / keyframecontrol
- issue 14 (#39) — NodeParamView group passthrough / context
- issue 20 (#45) — misc leftovers
**Person B — "project-load hook" chain (15 first, then its dependents):**
- issue 15 (#40) — nodeviewcontext structure core + **add the load hook**
- issue 16 (#41) — nodeview NODE_REMOVED_FROM_GRAPH (same area as 15)
- issue 13 (#38) — nodeparamviewwidgetbridge values (needs the hook)
- issue 17 (#42) — timelinewidget track/block structure (needs the hook; keeps 18's neighbor in one queue)
- issue 18 (#43) — trackviewitem index/muted
- issue 19 (#44) — projectviewmodel folder/label (needs the hook)
Rationale: B owns everything that consumes the issue 15 hook, so the hook's
API is designed and used by one person with no cross-team blocking. A's
batch only needs the already-landed issue 7 signal, so both can start today.
Workload is ~6 × 0.5 day each side.
Ground rules still apply per issue: `cmake --build cmake-build-debug -j8 &&
cd cmake-build-debug && ctest -j4` must be green (122/122) before shipping,
and remove the matching `bridge_->subscribe` / `oakengine_event_subscribe`
calls when done.